Thursday, December 1, 2016

BMHS Construction Update - December 1, 2016

What a difference 48 hours can make!  I went over to the high school site this afternoon to visit the enabling work that is happening with the construction entrance for the high school and was impressed to see how much work has happened since my last visit on Tuesday.  Here's what it looked like Tuesday morning from the (now former) bench on the first-base line of the baseball field:


And here's a similar view from this afternoon:


Although you can't quite get the view of what's been done from this angle - you can get a better view from the sidewalk across the street at the Parker School:


Or from the sidewalk on the high school side of River Street itself:


Doing all of this work now in the fall - prior to the ground freezing - puts us in a much better position with our schedule when full construction starts in spring 2017!