BMHS Construction Update - December 5, 2016

It's the first snowy morning of the 2016-17 school year, so it was a great morning to go out and walk the high school site and see the latest progress that was made over the weekend.  Work occurred on Saturday with tree-cutting equipment being brought onsite, and the results are dramatic:

From the Parker School entrance looking up River Street

From the Project Support/BEAM driveway, looking down River Street

From the Parker School driveway, looking at the construction road

From the southwest corner of the site, behind where the former baseball backstop

Shawmut is currently placing posts to put up the construction fence around the perimeter of the project site, starting closest to the ice rink; they are also doing cleanup work from tree removal activities.