Work for this week includes:

  • Shawmut site office build-out ongoing
  • Stormwater pollution prevention plan (SWPPP) activities to commence
  • Earthwork operations continue with grade strip and stock piling
  • Sanitary enabling operations to commence
  • Temporary and permanent draining operations to commence