Weekly Construction Update - April 24, 2017

The project hit another exciting milestone last week as the first concrete was poured on site!  The picture below was taken early Friday afternoon; approximately 100 cubic yards of concrete were placed that day!


Upcoming construction activities include:

  • Stripping, stockpiling, and trucking of loam is nearing completion.
  • The River Street connection to water services is complete and paving occurred on Saturday, April 22.  
  • Street cleaning and catch basin maintenance along River Street will be ongoing throughout spring and summer construction activities.
  • Temporary and permanent drainage measures, including Alumni Field basin, are nearing completion.
  • Soil nailing to prevent undermining of existing foundations is complete.
  • Site retaining walls are underway and will continue in the coming weeks.
  • Excavations for new foundations and footings is ongoing and on schedule.
  • The first concrete pour, along the south foundation wall, was placed on April 21!  Concrete deliveries will continue to ramp up over the coming weeks and throughout the summer.
  • Steel is expected onsite, beginning in area C, at the end of June.
  • Steel and elevated concrete floor decks will be completed through the summer and into fall 2017.