Tuesday, June 27, 2017

Weekly Construction Update - June 27, 2017

Yesterday marked another big milestone in the BMHS project as the first steel was erected on site!  It was amazing to see how much work was done in just one day - and it will be even more amazing for students and teachers to see what will be done when they come back from summer vacation!

The first beam being lowered into place at 9:00am

A view of the site at 2:45pm the same day

Here is this week's update on site activity:
  • New gas and electrical service coordination is ongoing with National Grid and is nearing completion.
  • Alumni Field's water service has been restored and the field is accessible.
  • All temporary stormwater facilities are in place and functioning and have performed as expected through recent rainfall.
  • Waterproofing and insulation of the foundation, then backfilling, compacting, and grading is underway in the academic wing of the building (sectors C, D, and E).
  • Foundation in sectors A and B are ongoing and are nearing completion.  Similar to the Academic wing, as these areas become complete, waterproofing, insulation, and backfilling will be underway.
  • Setting in structural steel base and leveling plates is underway throughout the Academic wing.
  • Setting of steel columns and structure began on June 26 and will continue through winter.  Approximately six truck deliveries per day will feed onsite steel progress 5-6 days per week through summer.
  • Completion of foundations in July will turn attention to pouring of the first concrete slabs both on grade and on completed elevated decks, starting in area A.

Friday, June 23, 2017

Hajjar Assistant Principal Finalists/Interviews

I am pleased to announce that there are two finalist candidates to be the next Assistant Principal at the Hajjar School, and that I will be conducting their public interviews on this coming Monday evening, June 26, in the Town Hall auditorium.  The finalists, with their times of their interviews are:

6:00  Ms. Kristen Pratt

Ms. Pratt is currently the Assistant Principal at the Center Woods Elementary School in Weare, NH.

7:15  Ms. Brittney Taylor

Ms. Taylor is currently the Principal of the K-8 Essex Academy at CREST Collaborative.

For those that would like to come to the public interviews, I encourage you to do so and would welcome your feedback afterwards.

Thursday, June 22, 2017

Yesterday marked the end of the 2016-17 school year, and I want to thank everyone involved in making it another great year for the Billerica Public Schools!  Thank you to our parents, to our staff, and particularly to our students - you make Billerica a great place to learn!

Yesterday also marked the final school day for eighteen of our friends and colleagues who have given 373 collective years to the Billerica Schools.  Our school system is better for all of them having been here, and we wish them all a long, happy, and healthy retirement:

Lisa Bejian, Grade 3 Teacher, Ditson
Denise Blanchet, Exec. Administrative Assistant, Central Services
Diane Cappella, House Secretary, BMHS
Debra Dagle, Reading Teacher, Ditson
Mary Durante, Paraprofessional, Parker
Karen Falzone, Paraprofessional, Parker
Christine Fanning, Special Education Teacher, Ditson
Cynthia Gladd-Walsh, Occupational Therapist, District
Rebecca Graham, Social Studies Teacher, Marshall
Ghalia Khelfaoui, Speech/Language Pathologist, Ditson
Judith Mason, Art Teacher, Ditson
Joan Mitza, Library/Athletics Secretary, BMHS
Linda Moody, Paraprofessional, Hajjar
Charlene Mullen, Grade 1 Teacher, Ditson
Donna O'Neil, Paraprofessional, Marshall
Annette Pelligrini, Special Education Secretary, Special Education
Deborah Robbins, Cafeteria Worker, Kennedy
Patricia Schneider, Paraprofessional, Parker

Thank you again to everyone for a great school year, and I hope that everyone has a restful and relaxing summer!

Tuesday, June 20, 2017

Weekly Construction Update - June 20, 2017

As we reach the end of the 2016-17 school year, it's amazing to see how much work has happened at the high school site over the past few months.  Check out below to see our most recent time lapse video, and subscribe to the New BMHS channel on YouTube to see all of our latest videos!




Here's this week's update:

  • A new water service main is installed off of River Street, and new gas and electrical services are nearing completion.
  • Access to Alumni Field has been limited since June 6 for completion of water service tie-in and temporary stormwater system.  Access will be restored on approximately June 21.
  • All temporary stormwater facilities are in place and functioning.
  • Concrete foundations are complete in the academic wing of the building (sectors C, D, and E).  Waterproofing, insulation, and backfilling is underway throughout this area.
  • The high foundation wall along the south facade of the Civic wing (sectors A and B) is complete, and foundations along the remainder of this area are nearing completion.  Similar to the Academic wing, as these areas become complete, waterproofing, insulation, and backfilling will be underway.
  • Setting in structural steel base plates is underway throughout areas with complete foundations and footings.
  • Earthwork remains underway to support foundation and first floor slab on grade installations and to process excess topsoil and rock for export and re-use on site.  Exporting of all soils not able to be re-used is underway and the stockpile is expected to be completely removed by the end of June.
  • Both structural steel and laminated wood structures are in the fabrication process in Canada.  The first steel deliveries are on trucks and on route to the site.
  • Structural steel erection will begin on June 26, and continue with multiple steel deliveries six days per week through summer.

New YouTube Video: BMHS Site Spring 2017

Monday, June 5, 2017

Weekly Construction Update - June 5, 2017

As we enter June, work continues to proceed rapidly onsite, and we are excited to know that the first delivery of steel is scheduled to begin at the end of this month!  

As for this week's update:
  • Temporary water service is installed into the site off of River Street.
  • Temporary gas service is nearing completion by National Grid and Shawmut, including abandoning the existing gas service that runs under sectors C and D of the new building.  This work, and associated water service work, will result in Alumni Field being closed from June 6 through June 21.
  • Temporary electrical services are anticipated to be brought into the site in June by National Grid, after which electrical ductbank routing for the new building will commence.
  • All temporary stormwater facilities are in place and functioning.
  • Concrete foundations are underway throughout the building, and sectors A and B are nearing completion.
  • Waterproofing and back-filling of soils against new foundation walls is underway as foundation become complete.
  • Earthwork remains underway to support foundation and first floor slab on grade installations and to process excess topsoil and rock for export and re-use on site.
  • Both structural steel and laminated wood structures are in the fabrication process in Canada.  Steel is expected onsite during the last week of June.
  • In the first few weeks of July, a second crane is anticipated to join the steel erection sequencing to keep pace with daily steel deliveries through fall 2017.



 Picture taken from Mr. Murphy's Office

Picture taken from stairwell above Special Education office 

Picture taken from Room 1307 (Memorial Building)